Translation Engine
A milestone in a Gantt chart becomes physical mass, a delivery window and a truck count.
Milestone input
From the contractor schedule
Area
5,000 m²
Compacted depth
150 mm
Delivery window
4 days
Material
Engine output
Tonnage required
1,814t
Truck loads
57@32t
Loads per day
15/ day
volume = 5,000 m² × 0.150 m = 750 m³
mass = volume × 2.24 t/m³ (density, CBR45 Road Base)
compacted = mass × 1.08 (compaction allowance) = 1,814 t
mass = volume × 2.24 t/m³ (density, CBR45 Road Base)
compacted = mass × 1.08 (compaction allowance) = 1,814 t
Downstream effect
What the quarry sees
{
"sector": "BNE C1",
"demand_group": "Commercial / Civil",
"material": "CBR45 Road Base",
"tonnes": 1814,
"window_days": 4,
"confidence": 0.88,
"builder": null
}
"sector": "BNE C1",
"demand_group": "Commercial / Civil",
"material": "CBR45 Road Base",
"tonnes": 1814,
"window_days": 4,
"confidence": 0.88,
"builder": null
}
No builder, no project, no address: just the mass, the sector and the window the fleet needs in order to plan.
Reference densities
CBR45 Road Base2.24 t/m³
20mm Aggregate1.55 t/m³
Fine Washed Sand1.6 t/m³
40MPa Ready Mix2.4 t/m³
Drainage Rock1.45 t/m³